Drivers using Bridge Connector and the Royal Avenue on-ramp to the stal̕əw̓asəm (Riverview) Bridge in New Westminster should plan for overnight lane closures and on-ramp closures this week.
The Pattullo Bridge Replacement notice dated August 28, 2026, says crews are conducting finishing works on the Agnes-Royal multi-use path overpass.
What road users should do
Bridge Connector users: Expect intermittent overnight single-lane traffic through the work area. One lane in each direction will be maintained. Follow signs and traffic control personnel.
Royal Avenue on-ramp users: When the on-ramp is closed, take 6th Street to 6th Avenue, then McBride Boulevard to Bridge Connector. Detour signage will be in place.
Commercial vehicles: Follow designated truck routes as directed.
Bridge Connector overnight closures
Intermittent single-lane closures on Bridge Connector:
- Started: Night of September 1, 2026
- Duration: Approximately one week
- Hours: 10 p.m. to 5 a.m.
Royal Avenue on-ramp overnight closures
The Royal Avenue on-ramp to the Riverview Bridge will be fully closed overnight:
- Friday, September 4: 9 p.m. to 5 a.m.
- Tuesday, September 8: 9 p.m. to 5 a.m.
- Wednesday, September 9: 9 p.m. to 5 a.m.
The on-ramp nights complete the overnight finishing window that started September 1 on Bridge Connector.
Who is affected
Drivers using Bridge Connector and the Royal Avenue on-ramp should plan for delays. Emergency responders cannot use the Royal Avenue on-ramp during closures and will use the McBride Boulevard detour instead. Commercial vehicles are detoured to designated truck routes. Nearby residents may hear some construction noise. Multi-use paths are not affected.
This overnight Bridge Connector and Royal Avenue on-ramp work is separate from the multi-month Front Street Truck Route closure, which involves a different corridor and continues through late 2026.
Contact
Questions about Pattullo Bridge Replacement construction can be directed to:
- 24/7 Information Line: 1-844-815-6149
- Website: pattullobridgereplacement.ca
- Email: pattullobridgeproject@gov.bc.ca
- Construction questions: info@fcgp.ca
Timelines are subject to change.